OCTA in cooperation with Caltrans is improving 16 miles of the San Diego Freeway (I-405) between State Route 73 (SR-73) and Interstate 605 (I-605). It also will construct the 405 Express Lanes from SR-73 to I-605. The new express lanes – incorporating the existing carpool lanes and connectors that opened in 2014 – will be two lanes in each direction.
View Closures & Detours:Bridge Milestones
The bridges highlighted below have recently reached a significant project milestone.
Now Open
Heil Avenue Pedestrian Bridge
- Complete
Improvements
- Newly improved bridge
- LED lighting for nighttime use
Now Open
Westminster Boulevard
- Complete
Improvements
- Newly improved bridge
- New bike lanes on both sides of the bridge
- New westbound sidewalk
Now Open
Fairview Road
- Complete
Improvements
- Newly improved bridge
Now Open
Edinger Avenue
- Complete
Improvements
- Newly improved bridge
- New westbound sidewalk
- New bike lanes on both sides of the bridge
Now Open
Edwards Street
- Complete
Improvements
- Newly improved bridge
Now Open
Magnolia Street
- Complete
Improvements
- Two new lanes of travel
- New bike lanes on both sides of the bridge
- New northbound sidewalk
Now Open
Talbert Avenue
- Complete
Improvements
- Two new lanes of travel
- New bike lanes on both sides of the bridge
Now Open
McFadden Avenue
- Complete
Improvements
- Two new lanes of travel
- New bike lanes on both sides of the bridge
- New eastbound sidewalk
Now Open
Bushard Street
- Complete
Improvements
- Newly improved bridge
Now Open
Slater Avenue
- Complete
Improvements
- Newly improved bridge
In Progress
Brookhurst Street
- Phase 1 Complete
- Bridge Open to Traffic During Construction
Improvements
- Newly improved bridge
- New bike lanes on both sides of the bridge
In Progress
Bolsa Avenue
- Phase 1 Complete
- Bridge Open to Traffic During Construction
Improvements
- Two new lanes of travel
- New bike lanes on both sides of the bridge
- New westbound sidewalk
In Progress
Bolsa Chica Road
- Phase 1 Complete
- Bridge Open to Traffic During Construction
Improvements
- Four new lanes of travel
- New bike lanes on both sides of the bridge
In Progress
Goldenwest Street
- Phase 1 Complete
- Bridge Open to Traffic During Construction
Improvements
- Three new lanes of travel
- New bike lanes on both sides of the bridge
- New southbound sidewalk
Latest Activity
Closures and Detours
Closures and Detours
Tuesday, March 21, 2023
Weekly Construction Alert
Closures and Detours
Closures and Detours
Friday, March 10, 2023
Closures and Detours
Closures and Detours
Friday, March 10, 2023
Closures and Detours
Closures and Detours
Wednesday, March 8, 2023
Closures and Detours
Closures and Detours
Thursday, March 2, 2023
Closures and Detours
Closures and Detours
Thursday, March 2, 2023
Closures and Detours
Closures and Detours
Wednesday, February 8, 2023
Closures and Detours
Closures and Detours
Wednesday, February 8, 2023
Closures and Detours
Closures and Detours
Wednesday, February 8, 2023
Social Media Feed
Contact the 405 Community Outreach Team
If you have questions, please contact the Outreach Team by calling (888) 400-8994.